Tlou Energy Ltd is developing energy solutions in Sub-Saharan Africa through gas-fired power and ancillary projects. The Lesedi Gas-to-Power Project is 100% owned and is the company's most advanced project. Tlou's competitive advantages include the ability to drill cost-effectively for gas, operational experience and Lesedi's strategic location in relation to energy customers.
351 stories · page 1 of 18
Archive
Today's Oil and Gas Update: Tlou Energy and more...
Market Update: 13 April 2023Rex International* (SGX: 5WH) - 1Q production up q/qLON:TLOU - Lesedi-6 drilling aheadLON:SYN - Pump delivery in 2QLON:JSE - Production guidance disappointsLON:SQZ - Strong start to the yearEnergy NewsBrent Oil U
Tlou Energy reports progress across Lesedi development
A key focus in the coming year is to drill more production wells for the 10MW project, the company said
Tlou Energy raises A$3mln for Lesedi project as Dr Campbell ups stake to 19.23%
“This is a further and significant endorsement of Tlou's Lesedi Power Project in Botswana," chief executive Anthony Gilby said
Tlou Energy raises A$2mln through a placing with a new strategic investor
Anthony Gilby, chief executive officer of Tlou said: "We have been working to secure the next series of funding partners for the company for some time and we are delighted to have reached agreement with the first of these being Dr Ian Campb
Tlou Energy denies breaking rules after paying greenwashing fine
Tlou paid the fine to the Australian regulator, but denied any wrongdoing
Tlou Energy highlights £3.3mln cash position in update on Botswana projects
Design and surveying for a gas fired power facility at the Lesedi project is complete, the company said
Tlou Energy provides update on construction of power transmission line for plant at Lesedi in Botswana
The overall progress achieved is 11%, up from 8% reported last month, although the planned target was 17% indicating a slippage of 6%
Tlou Energy's transmission line on track
“Work on the transmission line is scheduled for completion in mid-2023"
Tlou Energy begins to connect Lesedi Power Project to Botswana power grid
Work on the transmission line is scheduled for completion in mid-2023, with the sale of electricity starting in the second half of next year
Tlou Energy quarterly report highlights strong cash position
The company continues to advance its Lesedi gas-to-power project in Botswana
Tlou Energy appoints transmission line contractor
Building the overhead line is expected to take approximately 15 months to complete
Tlou Energy looks forward to Lesedi development after achieving targets
Lesedi was just the start with “ the potential to develop this project into hundreds of MW's of power"
Tlou Energy's JV with Synergen provides multiple opportunities, broker says
Tlou is progressing hydrogen production via pyrolysis of CBM with technology developer Synergen Met