Skip to main content
The Markets by Proactive
Go to Proactive UK
Proactive UK has moved. Proactive’s coverage of London’s small caps continues on proactiveinvestors.com Go there →
Advertisement
The Markets
by Proactive
Proactive UK has moved.
Coverage of London’s small caps continues on proactiveinvestors.com
Go to Proactive UK
The Markets
by Proactive
Proactive UK has moved.
Small-cap coverage continues on .com
Go to Proactive UK
Advertisement
The Markets
by Proactive
Proactive UK has moved.
Small-cap coverage continues on .com
Go to Proactive UK

Mining

Prospect Resources nears production from pilot plant at Arcadia Lithium Project

The company’s Arcadia Project team has met the development timeline with the completion of approximately 92% of the works required to start production at its petalite pilot plant.

Prospect Resources Ltd (ASX:PSC) has completed around 92% of the engineering, procurement and construction (EPC) scope for its high purity petalite pilot plant at the Arcadia Lithium Project in Zimbabwe.

According to the company, development work on the pilot plant has been progressing on schedule and is within the budget.

The company expected to achieve the first ore to the commissioned crusher circuit by the end of May.

EPC milestones completed on schedule and budget include:

  • Flowsheet and detailed engineering;
  • Procurement of equipment;
  • Power supply connection and reticulation on-site;
  • Laboratory and campsite ready for pilot plant operation;
  • Ore stockpile prepared to feed crushing circuit;
  • Earthworks and civil works completed; and
  • Pre-assembled DMS unit on route to the site.

“Meet development timeline”

Prospect Resources managing director Sam Hosack said: “The Arcadia Project team has continued to meet the development timeline and I’m pleased to announce that we have completed approximately 92% of the works required to commence production at our Pilot Plant.

“With lithium market sentiment and prices having increased through 2021, a strong cash balance and the company being shovel-ready to develop the Arcadia Project, Prospect Resources is well-positioned to make the transition to development and production.”

The company has appointed the operations team for the Pilot Plant, with key personnel holding significant lithium operational experience.

Additional tonnes

Prospect’s offtake partner Sibelco has requested additional tonnes over and above the original planned 200 tonnes so that they can seek qualification with a greater number of customers across Europe and Asia.

The company has also expanded engagement with a range of strategic groups from across Japan, China and Europe in recent months, who have an interest in spodumene offtake and assisting with the development of the project.

Prospect is set to produce laboratory spodumene samples for a number of these parties over the coming weeks to facilitate further due diligence on the Arcadia Project.

Early delivery of the product will ensure homologation can be achieved in the customers’ production process and will establish clear additional demand for the product within the industry.

This will assist the company in leveraging the value of the Arcadia project as a leader in the supply of high-quality spodumene products.

Welcoming the President

The company expects the President of Zimbabwe ED Mnangagwa to preside over the first production of high purity petalite from the pilot plant, which is likely to happen this month.

Prospect looks forward to welcoming the President, government officials and existing offtake partners to the site for the ceremony.