Salt Lake Potash Ltd's (ASX:SO4) (LON:SO4) (OTCMKTS:WHELF) (FRA:W1D) Tony Swiericzuk tells Proactive's Andrew Scott its Lake Way project in Western Australia is nearing completion, with the process plant 88% complete and the overall project, including all on-lake infrastructure 81% complete. Process plant commissioning is expected to begin in February, with introduction of first feed salts to the plant in March.
Salt Lake Potash focused on plant commissioning as Lake Way nears completion