Skip to main content
The Markets by Proactive
Go to Proactive UK
Proactive UK has moved. Proactive’s coverage of London’s small caps continues on proactiveinvestors.com Go there →
Advertisement
The Markets
by Proactive
Proactive UK has moved.
Coverage of London’s small caps continues on proactiveinvestors.com
Go to Proactive UK
The Markets
by Proactive
Proactive UK has moved.
Small-cap coverage continues on .com
Go to Proactive UK
Advertisement
The Markets
by Proactive
Proactive UK has moved.
Small-cap coverage continues on .com
Go to Proactive UK

Exploration & Production

Altech Chemicals ahead of schedule with electrical substation at HPA plant in Malaysia

The substation is expected to be completed during April 2020 with major structural works now complete.

Altech Chemicals Ltd (ASX:ATC) continues to progress construction of the key electrical substation within the high purity alumina (HPA) plant site in Johor, Malaysia and is now ahead of schedule.

Major structural works are complete and the majority of external detailing of the building has been finished.

The EPC consortium comprising SMS group and Metix and sub-contractors have started internal finishing and architectural detailing, completing sewerage and drainage works, and finalising vehicle access requirements.

The substation is now expected to be completed next month, about four weeks ahead of schedule.

North aspect of construction progress

Handover of the building to Altech will take place after final inspection and the identification of any punch list items.

The substation will be turned over to the local electricity service provider TNB (Tengaga Nasional Behad) for inspection by its project team ahead of switchgear installation, which is planned in parallel to the HPA plant construction to ensure electricity supply is available well in advance of plant commissioning.

At the end of February, the EPC construction consortium and subcontractors had completed 125,303 lost time injury (LTI) free hours on site.

The stage-1 and 2 construction activities have seen a total of 253 employees and contractors inducted and work completed with one first-aid medical treatment case and zero lost-time injuries.