Resolute Mining achieves commercial production rates at Syama, begins automation commissioning

The company is targeting full commissioning of the world’s first fully automated underground gold mine for the third quarter of this year.

1561617166_syama-757.jpg
More than 38,500 tonnes were mined and hauled in the last week

Resolute Mining Limited (ASX:RSG) (LON:RSG) has achieved commercial rates of ore production at its Syama Underground Gold Mine in Mali, mining and hauling more than 80% of nameplate mine capacity.

The ramp up of ore production at Syama is continuing and automated loading on the sublevel cave production levels has begun.

Syama will be the world’s first fully automated underground gold mine and at full capacity will produce about 46,000 tonnes of ore a week, or 2.4 million tonnes a year, using a fully integrated automated mine fleet.

 

Resolute managing director & CEO John Welborn confirmed Resolute continued to deliver on the company’s strategic goals for 2019, adding that the Syama Underground Mine would transform the company.

He said: “Achievement of sustained rates of commercial production from the world’s first fully automated underground gold mine is a key milestone for Syama, for Resolute, and for the mining industry.

“I congratulate the Syama project team, our operations team, and all our partners on this success.

“We are now focused on continuing the successful production ramp up to nameplate capacity and the completion of full automation of all aspects of the sublevel cave during 2019.”

READ: Resolute Mining expects to begin trading on Main Market of LSE this week

After the start of sublevel caving in December last year, the ramp-up of Syama focused on infrastructure, development and the automation implementation program.

Underground fibre backbone and mine-wide wireless network has been commissioned from the portal to the automated haulage level while the surface automation control room is now fully operational.

This network enables the operation of the automated haulage loop, automated rehandle level, mine digitisation and production automation, all of which allow operators to monitor and control mine production in real time.

READ: Resolute Mining secures additional mining leases at Ravenswood Expansion Project in QLD

The next phase of automation work will see the commissioning of the 1055 haulage level with automated rehandle loaders and haulage trucks working together to load from an ore pass and truck directly to the surface run-of-mine pad.

With the fans, pump stations, control room and communications network complete, the automation project is being progressively handed over to the operations team which is now at normal operational manning levels.

Quick facts: Resolute Mining Ltd

Price: $1.60

Market: ASX
Market Cap: $1.44 billion
Follow

Add related topics to MyProactive

Create your account: sign up and get ahead on news and events

NO INVESTMENT ADVICE

The Company is a publisher. You understand and agree that no content published on the Site constitutes a recommendation that any particular security, portfolio of securities, transaction, or investment strategy is...

In exchange for publishing services rendered by the Company on behalf of Resolute Mining Ltd named herein, including the promotion by the Company of Resolute Mining Ltd in any Content on the Site, the Company...

FOR OUR FULL DISCLAIMER CLICK HERE

Watch

Gold expected to surge even higher on back of global economic weakness

Mining Capital's Alastair Ford discusses what he describes as the stunning rise in gold as it's moved through $1500 this week. ''There are some pundits around who think it'll go higher, $1525 is the next target they're setting''. ''I think there is some likelihood it will go higher - the...

2 weeks, 3 days ago

3 min read