W Resources higher as it commences commissioning of jig and mill plant at La Parrilla

W Resources is moving towards the completion of its two million tonne per annum plant
W Resources higher as it commences commissioning of jig and mill plant at La Parrilla
Michael Masterman on site in Spain

W Resources PLC (LON:WRES) shares were higher on Tuesday as the firm commenced the commissioning of the jig and mill plant at its La Parrilla tungsten project in Spain.

The jig and mill plant will upgrade the La Parrilla ore, efficiently reject barren material, and prepare material for feed to the concentrator plant. The upgraded and milled mine feed will allow for a significant upgrade in production rates.

WATCH: W Resources showcases new La Parilla jig and concentrator in Spain

In parallel, development work on the new large scale concentrator plant has advanced over the last three weeks with 90% of all structural steel and primary equipment now on-site and being installed. The large concentrator plant is scheduled for construction completion this quarter.

The mine is primed for scale-up, with preparatory grade control drilling completed and the ramp from the Fast Track Mine (FTM) area to the crusher plant also completed. The first hard rock blasting of the 10 metre benches in the FTM area is also scheduled for this month.

"The commencement of commissioning the La Parrilla jig and mill plant following construction completion is a very important milestone as we advance to full completion of the two million tonne per annum plant,” said W Resources chairman Michael Masterman.

“We expect to be able to feed crushed ore to the jig and mill plant in late April and then process it through our existing concentrator plant. This will allow a significant increase in near term tungsten and tin production capacity.”

In afternoon trading, shares in W Resources were up 2.8% at 0.55p.

 -- Adds share price --

 

View full WRES profile View Profile

W Resources PLC Timeline

Related Articles

Pamlico project picture
June 23 2019
Newrange is earning into 100% of its flagship project via staged annual payments up to 2044
A drill rig at the Australian Vanadium project in WA
April 15 2019
A revised resource model is on the agenda for the US$616 million The Australian Vanadium Project.
King Island off the state of Tasmania hosts the old Dolphin tungsten mine
April 08 2019
The company today unveiled a production offtake agreement with a Sandvik-owned tungsten supplier.

© Proactive Investors 2019

Proactive Investors Limited, trading as “Proactiveinvestors United Kingdom”, is Authorised and regulated by the Financial Conduct Authority.
Registered in England with Company Registration number 05639690. Group VAT registration number 872070825 FCA Registration number 559082. You can contact us here.

Market Indices, Commodities and Regulatory News Headlines copyright © Morningstar. Data delayed 15 minutes unless otherwise indicated. Terms of use