Skip to main content
The Markets by Proactive
Go to Proactive UK
Proactive UK has moved. Proactive’s coverage of London’s small caps continues on proactiveinvestors.com Go there →
Advertisement
The Markets
by Proactive
Proactive UK has moved.
Coverage of London’s small caps continues on proactiveinvestors.com
Go to Proactive UK
The Markets
by Proactive
Proactive UK has moved.
Small-cap coverage continues on .com
Go to Proactive UK
Advertisement
The Markets
by Proactive
Proactive UK has moved.
Small-cap coverage continues on .com
Go to Proactive UK

Mining

Walkabout Resources highlights robust nature of Lindi Jumbo Graphite Project

The updated PFS shows working costs, production rates, reserve grades were not affected.

Walkabout Resources Ltd (ASX:WKT) has delivered a Definitive Feasibility Study (DFS) update for the proposed open pit mine and graphite processing plant at its Lindi Jumbo Graphite Project in south eastern Tanzania.

Walkabout holds 70% of Lindi with an option to acquire the remaining 30% share.

The update follows the subsequent Tanzanian legislative changes and further metallurgical testwork, and has been modelled employing only the Ore Reserve.

This reserve contains Proven and Probable Ore Reserves of 5 million tonnes at 16.13% total graphite contained for 809 kilo-tonnes of graphite concentrate, and comprises 42% of the Measured and Indicated Resources only.

Importantly from the update - working costs, production rates, reserve grades were not affected.

Highlights

- The DFS has been simultaneously updated in several areas;

  • Tanzanian legislative effects and 16% ownership modelled.
  • Revised capital estimate following Jinpeng initial estimates.
  • Revised concentrate ratios following BGRIMM testwork.
  • Adjustment of schedule allowing for delays due to legislation.

- Project start-up capital has now been reduced from US$38.7 to US$29.6 million, a saving of US$9.1 million, lowest capital intensity amongst peer group;

- Pre Tax NPV of US$302 million against previous of US$320 million and Pre Tax IRR now at 108% from previous of 96%;

- Post Tax NPV10 of US$180 million against previous of US$230 million and Post Tax IRR adjusted to 88% against previous 86%;

- Weighted average (Base Case) basket price of product is reduced to US$1,564 per tonne from US$1,687 per tonne as a result of modified metallurgical product mix;

- Pre Tax NPV of US$146 million when pricing 2017 graphite prices sourced from UBS report and actuals;

- Gross financial effect of Tanzanian 16% free carry (if it eventuates) and 1% clearing fee is US$101 million over life of mine or 8.4% of total revenue; and

- Modelling and design now using updated concentrate ratios based on large scale, closed circuit metallurgical test results from BGRIMM provides a higher level of certainty to study results.