Alara Resources Ltd (ASX:AUQ) is advancing towards construction of site infrastructure at the 70% owned Al Hadeetha copper-gold project in Oman.
Construction of a 1 million tonnes per annum copper concentrator and other site infrastructure is planned to commence during Q1 2017.
Alara has also identified project financing options in excess of the forecast capex, having already invested US$9 million with its joint venture partner.
Financing is subject to the issuance of the mining licence and Alara is not aware of any reason why the licence could not be issued in order to meet first production, scheduled for 2018.
Recent infill drill results are currently being incorporated into a revised resource model, with an update expected this week.
Background
Alara has a portfolio of projects in the Middle East and was focused on an infill drilling program during the June quarter at the 70% owned Al Hadeetha Copper-Gold Projects in Oman.
The company has completed an advanced scoping study on both the Daris and Al Hadeetha Copper-Gold Project in Oman.
Most recently it completed a feasibility study for the Washihi deposit within the Al Hadeetha project.
The company has completed a definitive feasibility study on the Khnaiguiyah Zinc-Copper Project in Saudi Arabia, which is the subject of legal proceedings.
The company is transitioning to establish itself as a base and precious metals mine development and production company.
Al Hadeetha Copper-Gold Project: Washihi
The Washihi JORC Resource estimates have been updated to comply with the 2012 code and are now being revised to incorporate the results of the recent drill program.
The current Washihi resource contains 14.1 million tonnes at 0.80% copper and 0.18 g/t gold.
Washihi’s Indicated Resource can be converted into a Reserve only after a mining licence is issued.
The Washihi mining licence application was first submitted in April 2013.
Project management proposals to bring Washihi into operation are currently being assessed with contract awards expected in the last quarter of the year.
Project financing
Alara has successfully identified project financing options in excess of the forecast capex required to construct the project.
With US$9 million having already been invested in the project by Alara and its joint venture partners, indicative bank finance underpinning up to US$40 million more, and alternate financing options including vendor finance and offtakes to fill the US$10 million gap.
Financing options are subject to the issuance of the Washihi Mining Licence by Oman’s Public Authority of Mining.
Oman supporting mining
Oman has been taking steps to support the country’s mining industry with the government promoting and prioritising its development.
Mining Development Oman has been capitalised with A$200 million and plans to raise a further A$130 million through IPO on Oman’s stock exchange before the end of the year.
Late last year the Public Authority for Mining in Oman submitted a draft of the new mining law for approval by relevant ministries.
The new law is expected to help attract investment to develop the mining sector into a major contributor to the country’s gross domestic product.
The mining sector is also preparing for an international mining and minerals conference, to be held in Muscat in January.
Proactive Investors Australia is the market leader in producing news, articles and research reports on ASX emerging companies with distribution in Australia, UK, North America and Hong Kong / China.