Anglo Asian Mining PLC (AIM:AAZ, OTC:AGXKF) has announced the resumption of normal flotation processing at its Gedabek operation in Azerbaijan.
The facilities are now operating at full capacity, processing ore from both stockpiles and the main open pit.
This follows the restart of the agitation leach plant in September after a 12-month halt.
The resumption of the leaching plant followed authorisation to raise the wall of the mine’s tailing dam on 5 August 2024, when the commissioning of the restart of its agitation leaching plant began.
As announced today, Anglo Asian has completed the first stage of raising the wall of the tailings dam.
Anglo Asian has committed to adopting the Global Industry Standard on Tailings Management to prioritise safety and environmental protection at its operations.