Skip to main content
The Markets by Proactive
Go to Proactive UK
Proactive UK has moved. Proactive’s coverage of London’s small caps continues on proactiveinvestors.com Go there →
Advertisement
The Markets
by Proactive
Proactive UK has moved.
Coverage of London’s small caps continues on proactiveinvestors.com
Go to Proactive UK
The Markets
by Proactive
Proactive UK has moved.
Small-cap coverage continues on .com
Go to Proactive UK
Advertisement
The Markets
by Proactive
Proactive UK has moved.
Small-cap coverage continues on .com
Go to Proactive UK

Gold & silver

G Mining Ventures says Tocantinzinho on track to start production in 2024

G Mining Ventures Corp (TSX-V:GMIN, OTCQX:GMINF) reported that its Tocantinzinho gold project in Pará, Brazil, is on track and within budget to start commercial production in the second half of 2024.

The project, which is 93% complete, has achieved significant construction and pre-production milestones.

The company has expended $447 million, representing 98% of the project’s total budget, and maintains a safety record with a Lost Time Incident Frequency Rate of 0.04 after over 5.2 million person-hours worked.

Construction is 95% complete with the mill installation nearing mechanical completion, G Mining reported.

The company has excavated 12.4 million tonnes from the starter pit, including 1.5 million tonnes of ore stockpiled ahead of schedule.

And a 193-km 138 kV transmission line is operational, supplying power to the site from the national grid, according to a statement from the company.

The project, benefiting from a strong gold market with prices around $2,400 per ounce, is progressing through the commissioning phase of its process plant and associated infrastructure. All plant employees are undergoing comprehensive training to ensure smooth operations post-commissioning.

G Mining Ventures has recruited 1,507 employees and contractors, with 94% being Brazilian nationals. The workforce peaked at 2,220 in August 2023, with reductions primarily in construction-related roles as the project advances towards operational readiness.

G Mining plans to start process plant commissioning in the current quarter.

It is aiming to start commercial production by the end of 2024.