Blue Star Helium Ltd (ASX:BNL, OTC:BSNLF) CEO Trent Spry tells Proactive the company’s initial production well, BBB #33, at the Voyager Project in Colorado, USA, is scheduled to spud in the week commencing November 27. Drilling contractor, Hydro Resources Rocky Mountain Inc, has advised that it will spud BBB #33 following the completion of their current job. Final site works are being undertaken and a spudder rig will be used to set the surface conductor in preparation for arrival of the main drill rig. Drilling operations are expected to take six to 10 days to reach planned total depth (TD) of drilling. The well will be wireline logged at TD for two days after which it will be flow and pressure tested for five days.
Blue Star Helium gearing up to spud initial production well