08:00 Mon 04 May 2020
Bushveld Minerals Ld - Q1 2020 Operational Update
Market Abuse Regulation ("MAR") Disclosure
Certain information contained in this announcement would have been deemed inside information for the purposes of Article 7 of Regulation (EU) No 596/2014 until the release of this announcement.
("
Q1 2020 Operational Update
Key Highlights
Vametco
· Production for Q1 2020 was 652 mtV (482.5 mtV 74 per cent net attributable interest) in the form of Nitrovan, marginally ahead of Q1 2019 production of 649 mtV despite being impacted by the Covid-19 nation-wide lockdown as well as higher than usual rainfall during the quarter.
· Sales of 898 mtV (664.5 mtV 74 per cent net attributable interest) achieved in Q1 2020, 77 per cent higher than Q1 2019 as a result of additional production volumes in Q4 2019 and increased customer demand.
· Underlying production cost of
· Early completion of the annual maintenance programme, which was initially planned for Q2 2020 for a period of 10 days. No further maintenance shutdowns are planned for the remainder of 2020.
· In line with the Government's "risk-adjusted strategy for economic activity", following a 35 days Covid-19 lockdown production is ramping up to normal levels.
Vanchem
· Solid operating performance, with production of 219 mtV despite being impacted by 10 days of power rationing as well as the Covid-19 lockdown during the quarter. Vanchem's production for Q1 2020 represented 31 per cent of total Bushveld attributable vanadium production.
· Sales of 182 mtV achieved comprised of a range of products during the quarter.
· The underlying production cost for the quarter was
· Completed the scoping study of a refurbishment programme and prioritised a total of around R85 million as critical capital spend required for 2020 to enable Vanchem to continue to sustainably operate. We expect to incur most of the spend during the second half of the year.
· As with Vametco, production is ramping up to normal levels following Government guidance.
Bushveld Energy
· Approved construction of vanadium electrolyte plant, including receipt of funding approvals for equity and debt from the
· In line with its strategy of partnering with Vanadium Redox Flow Batteries ("VRFB") companies, on 1 April Bushveld announced that it held a 8.71 per cent shareholding in Invinity Energy Systems plc ("Invinity") the entity created by the merger of
· Completion of due diligence to acquire Enerox as part of an investment consortium.
Capital structure and liquidity
· As previously reported, on
· As the near-term impact of Covid-19 on operating conditions is uncertain, the Group is taking cash preservation measures to manage near term liquidity while preserving the long term sustainability of the assets. These include reviewing and limiting operational expenditure where necessary as well as deferring some growth associated (non-critical) capital expenditure across the mining, processing and energy businesses.
Outlook
· 2020 production and cost guidance for both Vanchem and Vametco remains under review and will remain so until the Company is in a position to quantify the impact of the Covid-19 pandemic and the South African nation-wide lockdown.
Fortune Mojapelo, CEO of
"This update comes in the midst of the global Covid-19 pandemic that has not only changed our world but will continue to change it in ways we have not fully understood yet. I am pleased that these difficult circumstances found
"We are fortunate to operate in a country whose leadership has taken early decisive action to limit the spread of the Covid-19 virus while ensuring that we build the necessary public health care capacity and identify fiscal responses to manage the coming wave of infections, while treatments and vaccines are still under development. Navigating this situation requires us to meet the immediate challenges of ensuring the safety and health of our workers, sustain business continuity and ensure readiness to scale back up to full capacity in due course, while also supporting the fight against Covid-19 among our host communities.
"We used the lockdown period to strengthen our health and safety protocols together with business continuity measures, conducted maintenance and processed intermediary stockpiles, as per the guidelines received from our authorities. We are pleased that both Vametco and Vanchem are safely increasing production to normal levels.
"I am glad that our suppliers and service providers have continued operating and servicing the Company. We have continued to pay our employees during the lockdown, have not had to declare force majeure while continuing to meet our customer orders. In addition, we have carried on playing a supportive role in our local communities by supplying water and sanitisers to local hospitals, police stations and old age homes. I am particularly proud of the management team that has worked so hard to ensure the Company is not only prepared to weather the Covid-19 storm but does so with empathy and responsibility to all our stakeholders.
"From a liquidity perspective, we started the year with a healthy cash balance. We retain a cautiously positive growth outlook on the vanadium market and the Company's role therein. This notwithstanding, we have undertaken a review of our capital spending, deferring some non-essential capital expenditure for the near term whilst preserving the long term integrity of our business and still positioning the company for growth in the vanadium market in the medium to long term. Furthermore, to enhance our liquidity position and financial flexibility we drew down the full
"We are confident that the measures we have taken will enable us to build an even more resilient
"We are releasing this announcement later than we would have typically done. This has been necessitated by the need to better understand and so provide clarity on the impact of the pandemic and the fast-evolving environment and regulatory landscape we are operating in. We also expect to be in a better position to disclose more on our renewed plans and capital expenditure requirements in our 2019 full year results announcement, when we believe there will be more clarity on what the rest of the 2020 financial year will hold.
"Our intention is to continue adapting to this fluid environment and do everything necessary to protect our people and our business, while doing our part to fight this global pandemic."
Conference call
fBushveld Minerals Chief Executive Officer,
Tel:
Toll Free:
Pin: 47594360#
Alternatively, a list of international dial-in numbers are available here:
https://events-ftp.arkadin.com/ev/docs/NE_W2_TF_Events_International_Access_List.pdf
A replay of the conference call will be available on the Company's website post the call.
Covid-19 Response
The Company rapidly developed and implemented a detailed programme in response to the Covid-19 pandemic. The programme prioritises the protection of its employees and host communities through rapid implementation of health and hygiene controls in the workplace, protocols for dealing with suspected cases of infection and business continuity measures to minimise the disruption effects of the pandemic on the business.
§ Health and Safety: designing and implementing protocols aligned to those provided by the
§ Human Resources: proactively managing the workforce; focusing first on the high priority vulnerabilities and establishing business continuity measures and protocols to enable the organisation to adapt as the epidemic unfolds.
§ Finance: establishing cash preservation measures to manage near term liquidity while preserving the long term sustainability of the assets. These include reviewing and limiting operational expenditure where necessary as well as deferring growth associated (non-critical) capital expenditure.
§ Information Technology: assessing and addressing systems and cyber vulnerabilities whilst enabling the teams across the sites to work and collaborate remotely
§ Supply Chain: ensuring security of supply chain, specifically, anticipating potential disruptions and putting in place sufficient contingency plans. Bushveld continues to work with customers to fulfil orders and meet their requirements while still complying with Government directives. The supply chain is open and customer orders remain robust.
§ Stakeholder and Community: continued engagement and collaboration with employees, Government, and communities to reduce the impact on society.
§ Customers: engaging with our customers and leveraging our existing relationships to secure demand post the current lockdown.
§ Medium term and Vanadium market outlook: understanding and planning for the impacts of Covid-19, beyond the immediate disruption to our operations and the markets we operate in. Despite the impact of Covid-19 the vanadium price has been resilient across all regions.
Looking ahead we expect vanadium demand to remain robust in the medium to long term spurred on by supportive fiscal stimulus and increased infrastructure investments. Growing calls to take advantage of the fiscal stimulus opportunities to accelerate the energy transition are also expected to provide further support to the growth of the energy storage industry in which VRFBs have a significant role to play.
Our protocols have functioned effectively, and we will continue to monitor the situation and update our measures in line with the guidelines from the South African health authorities and Government.
Bushveld Vanadium
Bushveld has one of the largest, high-grade primary vanadium resource bases in the world. The Company's vanadium resource base currently consists of three mineral assets, Vametco, Brits and Mokopane, and its processing facilities consist of Vametco and Vanchem, which are all situated in
While Bushveld Vanadium was initially operating at the run-rate required to meet its 2020 guidance at Vametco and Vanchem, this was interrupted when the South African Government issued a directive on 23 March for a 21 days nation-wide lockdown effective from midnight on 26 March, for all citizens, to minimise movement of non-essential businesses and activities. On 9 April, the Government announced a two week extension of the lockdown period to 30 April.
As per the Amended Disaster Regulations announced by the South African Government on 16 April, mining operations were allowed to re-open and operate at a reduced capacity of 50 per cent of normal production levels during the lockdown period.
On 23 April, the Government announced that it will follow a "risk-adjusted strategy for economic activity". The approach proposes five alert levels, with five being a hard lockdown and one being where normal activity can resume. Different parts of the country may be at different alert levels at any one time, with levels adjusted up or down based on the rate of transmission in each area. The Government announced that the country's lockdown would move to level four on 1 May, where open-cast mining will be allowed to scale up to full employment and supply chains for permitted goods and services will be allowed to recommence.
Consequent to the disruption in production during the lock down period there is uncertainty around the operating outlook and Bushveld is reviewing its 2020 production and cost guidance for both Vametco and Vanchem. An update will be provided as part of the Company's 2019 full year result announcement once it has quantified the impact of Covid-19 and has more certainty on the road ahead.
Vametco
Table 1: Operational highlights for Vametco (on a 100% basis)1
Description |
Unit | Q1 2020 | Q1 2020 vs Q1 2019 | Q1 2020 vs Q4 2019 |
Vanadium (Nitrovan plus FeV) produced | mtV2 | 652 | 0.4% | -25.9% |
Vanadium sold | mtV2 | 898 | 76.9% | 33.4% |
Average LMB vanadium price3 | US$/kgV | 26.5 | -63.8% | 15.1% |
Average CRU RN vanadium price3 | US$/kgV | 27.2 | -69.1% | 4.3% |
Average Asian Metals price3 | US$/kgV | 24.2 | -55.9% | -5.3% |
Underlying production cash cost4 | ZAR/kgV | 289 | 0.6% | 34.8% |
Underlying production cash cost4 | US$/kgV | 18.9 | -8.1% | 29.3% |
1. Based on provisional, unaudited figures. Bushveld's net attributable interest of the above figures is approximately 74 per cent.
2. mtV = metric tonnes of vanadium.
3. The vanadium price is based on the FeV mid average price for the period, published by LMB for sales to
4. Excludes depreciation, royalties and selling, general & administrative expenses. Q4 2019 production cost decreased from
· Vametco's production for Q1 2020 was 652 mtV in the form of Nitrovan from magnetite concentrate, marginally ahead of Q1 2019's production (Q1 2019: 649 mtV) and 26 per cent lower than Q4 2019 (Q4 2019: 880 mtV). This decrease in production was due to:
Ø Excessive rains that caused flooding in the mining pit. Extra pumping capacity has since removed the water from the affected area;
Ø The nation-wide lockdown that was announced on 23 March and came into effect from midnight on 26 March resulting in several days of lost production in the quarter; and
Ø As previously communicated, the Group had guided for volumes to be weighted towards the second half of the year after Vametco completed the construction and commissioning of the kiln off gas facility, which has since been placed on hold due to Covid-19.
· Vametco sold 898 mtV in Q1 2020, which was 77 per cent higher compared to Q1 2019 (Q1 2019: 508 mtV) and 33 per cent higher than Q4 2019 (Q4 2019: 673 mtV), underpinned by additional volumes being available for sale as a result of the production volume increase in Q4 2019 and increased customer demand.
· Underlying production cost of
· Vametco was granted approval from the DMRE to conduct reduced scale operations. As a result, Vametco has successfully completed its annual maintenance programme, which was initially planned for Q2 2020. No further maintenance shutdowns are expected for the remainder of 2020.
· As per the Amended Disaster Regulations announced by the South African Government on 16 April, mining operations were allowed to re-open and operate at a reduced capacity of 50 per cent of normal production level during the period of the lockdown, under agreed precautionary measures with labour. Vametco restarted operations when it was grated the permit to ramp up to a 50 per cent capacity.
· In accordance with the "risk-adjusted strategy for economic activity", open-cast mining will be allowed to scale up operations to full employment from 1 May. As Vametco is an open-cast mine, it is ramping up activities to normal levels, under agreed health and safety measures.
· Vametco's 2020 production and cost guidance remain under review and will remain so until the Company is in a position to quantify the impact of the Covid-19 pandemic and the South African nation-wide lockdown.
· A JORC compliant Competent Persons Report ("CPR") for the updated Mineral Reserve and Resource Estimate for Vametco was published on the Company's website on
· Vametco sells the majority of its product to
Other projects underway at Vametco
· The kiln off-gas project has been placed on hold due to Covid-19 restrictions. A review of timing for completion of the project is being considered and further detail will be provided accordingly. The purpose of the kiln off-gas project is to comply with environmental regulatory requirements and further increase kiln feed throughput. Engagements with the relevant authorities are underway.
Vanchem
Table 2: Operational highlights for Vanchem
Description |
Unit | Q1 2020 |
Chemicals | mtV1 | 19.0 |
Flake | mtV1 | 130.5 |
FeV | mtV1 | 69.4 |
Total production | mtV1 | 218.9 |
Chemicals | mtV1 | 9.7 |
Flake | mtV1 | 75.1 |
FeV | mtV1 | 97.6 |
Total sales | mtV | 182.4 |
Underlying weighted average production cash cost2 | ZAR/kgV | 284.3 |
Underlying weighted average production cash cost2 | US$/kgV | 18.5 |
1. mtV = metric tonnes of vanadium.
2. Excludes depreciation and selling, general & administrative expenses.
· Production in Q1 2020 was 219 mtV. Operations were affected by the 10 days of power rationing during Q1 2020 as well as the nation-wide lockdown which was announced on 23 March and came into effect from midnight on 26 March.
Ø Production numbers are provided at the time of reporting, after which, based on customers' demand, Chemicals and Flake may be further processed to the required finished product, which will result in production and cost adjustments in line with the demand profiles of the various products.
Ø Vanchem's production for Q1 2020 represented 31 per cent of total Bushveld attributable vanadium production.
· Achieved sales of 182 mtV comprising of a range of products was also achieved during the quarter.
· The underlying production cost for the quarter was
· As per the "risk-adjusted strategy for economic activity", global business services for export markets will be allowed to recommence. Vanchem is ramping up activities to return to normal levels, under agreed precautionary measures.
· Completed the scoping study of a refurbishment programme and prioritised a total of around R85 million as critical capital spend required for 2020 to enable Vanchem to continue to operate sustainably. We expect to incur most of the spend during the second half of the year.
· Vanchem's 2020 production and cost guidance remain under review and will remain so until the Company is in a position to quantify the impact of the Covid-19 pandemic and the South African nation-wide lockdown.
Mokopane
· The definitive feasibility study ("DFS") to mine the Main Magnetite Layer based on the assumption that Mokopane will be the primary feedstock supplier to Vanchem. As part of Group's growth associated (non-critical) capital expenditure review, timing for the DFS is now under consideration. This does not affect's Vanchem's processing ability as it has sufficient ore supply to support current levels of production, until H1 2021. The Company retains the optionality to supply magnetite concentrates from Vametco to the Vanchem Plant.
Brits
·
· The Company's interest in the asset ranges between 51 per cent and 74 per cent through three different companies, one of which is Caber Trade Mining and Invest 1 (Pty) Ltd ("Caber Trade"), the mining right applicant, and in which the Company holds an interest of 51 per cent.
· The Caber Trade mining right application was recently refused by the DMRE due to not fulfilling certain conditions that had been set out in the 2012 letter of acceptance. Caber Trade has subsequently lodged an appeal against the decision on the grounds that the process followed in taking the refusal decision was administratively flawed.
· A JORC compliant CPR for the Maiden Mineral Resource was published on the Company's website on
Bushveld Energy
Manufacturing
· An investment decision was made on the vanadium electrolyte plant. The investment commitment from Bushveld is up to R68 million through 2022, which includes capital expenditure, working capital and ramp-up support.
· The IDC also approved the investment for its share of equity and all the debt funding for the project.
· The shareholding structure between Bushveld Energy and the IDC has been updated to 55 per cent for Bushveld and 45 per cent for the IDC, reflecting additional work Bushveld had conducted in 2015 and 2016 on the project, prior to entering into the Cooperation Agreement with the IDC. This also reflects the IDC's preference that Bushveld Energy should have control of the project.
· An Engineering, Procurement and Construction ("EPC") company was selected from among the tendered bids to build the facility in
·
Investment
· A loan of
Ø The ability of Invinity to secure more than
·
Impact of Covid-19 and South African lockdown
· Overall, our view of the situation is consistent with a recent assessment by IHS Markit in that "Despite a subdued year in 2019 and a challenging start to 2020 caused by the Covid-19 outbreak, the outlook for energy storage remains strong, with cumulative installations of grid-connected battery energy storage predicted to reach 64.3 GW / 179 GWh in 2025."
· Delays of several months are likely for our projects in
· In all our projects, we are also budgeting slightly longer supply chain times, including logistics, through H1 2021.
Lemur
· Lemur appointed a consultant to conduct the DFS, which commenced in Q1 2020 and is expected to be completed by the end of Q3 2020. Output of this study will be the mine design and scheduling for the Imaloto coal mine.
· The Social and Environmental Impact Assessment ("SEIA") studies are ongoing and on schedule with the coal and water samples currently undergoing tests in
· The EPC contract negotiations for the Imaloto power station with Sinohydro and the preferred bidder for construction of the transmission lines are ongoing.
· Engagement with potential lenders for project finance is still ongoing with the objective of achieving financial close now expected to occur within twelve months.
· Lemur is in continued discussions with Sinohydro, a subsidiary of state-owned
ENDS
Enquiries: [email protected]
| | +27 (0) 11 268 6555 |
Fortune Mojapelo, Chief Executive Officer | | |
| | |
| | |
| Nominated Adviser & Broker | +44 (0) 20 3470 0470 |
| | |
| | |
| | |
| Joint Broker | +44 (0) 20 7236 1010 |
| | |
| | |
| | |
| Joint Broker | +44 (0) 20 7418 8900 |
| | |
| | |
Tavistock | Financial PR | |
| | +44 (0) 207 920 3150 |
| | |
Brunswick | Financial PR ( | |
Miyelani Shikwambana | | +27 (0) 11 502 7300 |
ABOUT
The Company's flagship vanadium platform includes a 74 per cent controlling interest in
Bushveld's vision is to become a significant, low-cost, integrated primary vanadium producer through owning high grade assets. Whilst the demand for vanadium remains largely anchored in the steel industry,
The Company's approach to project development recognises that, whilst attractive project economics are imperative, they may be insufficient to secure capital to bring them to account. A clear path to production within a visible timeframe, low capital expenditure requirements and scalability are important factors in ensuring a positive return on investment. This philosophy is core to the Company's strategy in developing projects.
Detailed information on the Company and progress to date can be accessed on the website www.bushveldminerals.com.
About Vametco
Vametco is located near Brits on the
The Vametco mining operation uses open pit bench mining methods to mine a well-defined orebody. The deposit is continuous with limited faulting and dips in a northerly direction at approximately 19 degrees.
ROM ore is fed into a primary, secondary and tertiary crushing circuit, followed by milling and magnetic separation to produce magnetite concentrates. The magnetite concentrates are fed into the extraction process which includes the kiln for roasting followed by leaching and precipitation. Thereafter the precipitated vanadium as ammonium metavanadate is converted to modified vanadium oxide ("MVO") in rotary calciners. MVO is fed into the mix plant and finally into the shaft furnaces to produce NitrovanTM.
About Vanchem
Vanchem is situated at
About
Bushveld Energy is a leading energy storage solutions provider, focusing on the African market. Bushveld Energy recognises that electricity in
Bushveld Energy is focused on developing and promoting the role of vanadium in the growing global energy storage market through application in vanadium redox flow batteries. Its near term strategy is to deploy several VRFB systems as part of its longer term vision to become a significant electricity storage provider in
This information is provided by RNS, the news service of the
NO INVESTMENT ADVICE
The Company is a publisher. You understand and agree that no content published on the Site constitutes a recommendation that any particular security, portfolio of securities, transaction, or investment strategy is...
FOR OUR FULL DISCLAIMER CLICK HEREDeep dive
