EMED Mining rejects media report of delay at Rio Tinto project

EMED Mining rejects media report of delay at Rio Tinto project

EMED Mining (LON:EMED) said the licensing process for the re-start of the Rio Tinto copper project in Spain remains on track, rejecting a local media report on Wednesday that there was a three-month delay.

The company said it continues to work co-operatively on the licensing process with the Junta de Andalucia.

Last month, EMED said the Ministry of Environment and Land Planning of the Government of Andalusia had issued a compatibility report regarding the reopening of the mine that stated that there were no inconsistencies in any environmental aspects of the project.


Timeline

Related Articles

June 16
The high grade zones comprise 126 mln tonnes at 1.03% copper.
August 13
The award of a mining licence will fire the starting pistol on a period of frenetic activity.
January 28

EMED has now finally, once and for all, drawn the line under permitting and has now triggered the countdown to production.

© Proactive Investors 2015