Stocktube video
15/12/2011

Avalon Rare Metals CEO says feasibility study on target for late 2012

View full size
Additional Information
Market: TSX
Sector: General Mining - Rare Earth Minerals
EPIC: AVL
Latest Price: C$1.50  (0,00%)
52-week High: C$7.56
52-week Low: C$1.44
Market Cap: C$154.78M
1 year chart
1 day chart
Watchlist/Portfolio

Add to watchlist:

Only registered members can add into watchlist !

Register here !
Avalon Rare Metals
www.avalonraremetals.com

Avalon Rare Metals Inc. (TSX & NYSE Amex: AVL) is a mineral exploration and development company focused on rare metals deposits in Canada. Its flagship project, the 100%-owned Nechalacho Deposit, Thor Lake, NWT, is emerging as one of the largest undeveloped rare earth elements resources in the world. Its exceptional enrichment in the more valuable 'heavy' rare earth elements, which are key to enabling advances in green energy technology and other growing high-tech applications, is one of the few potential sources of these critical elements outside of China, currently the source of 95% of world supply. Avalon is well funded, has no debt and its work programs are progressing steadily. Social responsibility and environmental stewardship are corporate cornerstones. Avalon's performance on community engagement in the north earned it the 2010 PDAC Environmental and Social Responsibility Award.

 

Pdf

Avalon Rare Metals delivers progress update for Nechalacho, update resource expected soon

9th Nov 2011, 9:58 pm by Deborah Sterescu

Avalon Rare Metals (TSE:AVL) (AMEX:AVL) gave Wednesday a development update for its Nechalacho heavy rare earths project in Thor Lake, Northwest Territories, saying it is continuing to make steady progress towards defining the metallurgical process flowsheets, but work has come along slower than anticipated.

The company said though the results are positive, the slower than expected progress could result in a minor delay in the completion of the bankable feasibility study, but the overall schedule to production has not been impacted.

Recent metallurgical testwork has been focused on the flotation process for concentrating the rare earth bearing minerals. A 3.7 tonne continuous pilot scale concentrate production run was executed at SGS Minerals, confirming anticipated recoveries from the pre-feasbility study.

The recoveries reported in the study were 89.7% for zirconium oxide, 79.5% for all rare earth oxides,  68.9% for niobium oxide and 63% for tantalum oxide.

A 40 tonne bulk sample has been delivered to SGS for a full scale pilot plant trial scheduled to begin in late November or early December, the company said.

Hydrometallurgical testwork is also progressing with the initiation of pilot scale testing. After the initial tests are completed and one type of reactor chosen, longer duration tests will begin using concentrate from the 40 tonne flotation pilot plant.

Flotation and hydrometallurgical progress has been slower than anticipated mainly due to capacity issues with the company's service providers, it said, who have been experiencing high demand for processing and analytical services.

However, the company also completed the 2011 drilling program for the project in October, with an updated resource estimate for the Nechalacho deposit due out in December.

A major objective of the drill program in the past year has been to generate the 40 tonne bulk sample for metallurgical testing, with a large diameter PQ drill rig being one of the two rigs on the property. A total of 13,979 metres in 72 holes was drilled in the summer program, bringing the total drill production in 2011 to 26,203 metres in 137 holes. In addition to bulk sample collection, the campaign also provided detailed drilling in the areas targeted for initial mine development.

Drilling is scheduled to resume at the site in mid to late January 2012, with the objectives of detailed drilling of the area of the five year mine plan, and acquisition of additional bulk sample material.

With regards to permitting, Avalon completed and filed its Developers Assessment Report on in May, otherwise known as an Environmental Impact Statement. Earlier this month, the company received notification that it has been deemed in conformity with terms of reference by the Mackenzie Valley Environmental Impact Review Board, over five months after its submission - slower than expected.

"This has put the process behind schedule, creating some risk of a delay in receiving final operating permits," Avalon said in a statement.
 
Avalon is continuing discussions with the four Asian companies that have each signed a memorandum of understanding regarding off-take agreements. The four companies are interested in investing in Avalon's Thor Lake project in exchange for becoming partners in the project, and the right to purchase rare earth oxides for a period of time. Due diligence and negotiation meetings have been scheduled over the next few weeks with all four parties.

No binding agreements have yet been signed, the company concluded.

According to the latest economics assessment, the project is now estimated to yield a 34 percent internal rate of return, on an after-tax basis, compared to the prior estimate of 12 percent. The after-tax net present value also rose to C$1.27 billion, at a 10 percent discount rate, versus the earlier C$97 million.

The deposit's 20-year mine life is based on a probable mineral reserve estimate of 14.5 million tonnes of 1.53% total rare earth oxides (TREO), 2.90% zirconium oxide (ZrO2), 0.38% niobium oxide (Nb2O5) and 0.04% tantalum oxide (Ta2O5).

No investment advice

The Company is a publisher and is not registered with or authorised by the Financial Services Authority (FSA). You understand and agree that no content published on the Site constitutes a recommendation that any particular security, portfolio of securities, transaction, or investment strategy is suitable or advisable for any specific person. You further understand that none of the information providers or their affiliates will advise you personally concerning the nature, potential, advisability, value or suitability of any particular security, portfolio of securities, transaction, investment strategy, or other matter.

You understand that the Site may contain opinions from time to time with regard to securities mentioned in other products, including company related products, and that those opinions may be different from those obtained by using another product related to the Company. You understand and agree that contributors may write about securities in which they or their firms have a position, and that they may trade such securities for their own account. In cases where the position is held at the time of publication and such position is known to the Company, appropriate disclosure is made. However, you understand and agree that at the time of any transaction that you make, one or more contributors may have a position in the securities written about. You understand that price and other data is supplied by sources believed to be reliable, that the calculations herein are made using such data, and that neither such data nor such calculations are guaranteed by these sources, the Company, the information providers or any other person or entity, and may not be complete or accurate.

From time to time, reference may be made in our marketing materials to prior articles and opinions we have published. These references may be selective, may reference only a portion of an article or recommendation, and are likely not to be current. As markets change continuously, previously published information and data may not be current and should not be relied upon.