Amur Minerals completes ice road to its Kun-Manie project a week earlier than last year

Amur Minerals said that nine vehicle convoys are now transporting the supplies to Kun-Manie, its nickel sulphide deposit in Russia
Ice road
Two of eight planned trips have been completed and fuel, supplies, spares and food for the upcoming season have already been delivered

Amur Minerals Corporation (LON:AMC) said it has completed construction of the 350km long ice road from the Ulak station, on the Baikal-Amur rail line, to its Kun-Manie project a week earlier than last year.

The AIM-listed mineral exploration company, focused on base metal projects in the far east of Russia, said that the ice road was completed on February 15 and nine vehicle convoys are now transporting the supplies to Kun-Manie, nickel sulphide deposit in Russia.

READ: Amur Minerals sets out 2018 programme of works for Kun-Manie

Two of the eight planned trips have been completed and fuel, supplies, spares and food for the upcoming season have already been delivered.

With the new ice road being the most cost-effective way to resupply company’s operation, Amur Minerals said it will be in a position to diamond-0core drill a planned 15,000 metres and undertake several site investigation studies.

Robin Young, the company's CEO, said: “Operating on a 24 hour a day cycle, seven days a week, we anticipate successful and complete resupply of the site.”

He concluded: “The resupply will allow us to finish up the majority of our site investigative work for moving the project forward to a final production decision and design.”

In late afternoon trading, Amur Minerals' shares were 7.5% higher at 5.3p.

 -- Updates share price --

View full AMC profile View Profile

Amur Minerals Corporation Timeline

Related Articles

1519735283_nickel-periodic-1.jpg
February 27 2018
A major work programme is planned for Kun-Manie this year, which will allow for economic studies to take place
Horizonte Minerals has one of the largest undeveloped nickel saprolite projects in the world
May 30 2018
Horizonte has made steady progress in Brazil, and is now on the cusp of releasing a feasibility study for Araguaia

© Proactive Investors 2018

Proactive Investors Limited, trading as “Proactiveinvestors United Kingdom”, is Authorised and regulated by the Financial Conduct Authority.
Registered in England with Company Registration number 05639690. Group VAT registration number 872070825 FCA Registration number 559082. You can contact us here.

Market Indices, Commodities and Regulatory News Headlines copyright © Morningstar. Data delayed 15 minutes unless otherwise indicated. Terms of use