Jubilee Platinum nears commissioning of Dilokong plant

The two projects are predicted to process more than 900,000 tons of platinum surface tailings annually.
Jubilee Platinum nears commissioning of Dilokong plant
A second platinum tailings project, with ferrochrome giant Hernic, is also on track for the final quarter of this year

Jubilee Platinum (LON:JLP) is to commission its new platinum tailing processing plant at ASA Metals’ Dilokong chrome mine in South Africa this month.

Erection of its chrome plant has been carried out and final tie-ins for piping, electrics and controls are being completed, Jubilee said.

A second tailings project, with ferrochrome giant Hernic, is also on track for the final quarter of this year with pre-site work underway.

The two projects are predicted to process more than 900,000 tons of platinum surface tailings annually.

PhilW.jpg
Why Invest In Jubilee Platinum PLC? Read More Here

Register here to be notified of future JLP Company articles
View full JLP profile

Jubilee Platinum PLC Timeline

Related Articles

Copper-at-Kounrad.jpg
February 09 2016
Central Asia Metals has wowed markets with a strong share price supported by good operational margins and a healthy dividend regime. But can it continue?
Picture of a platinum dore bar
May 18 2016
As well as being a shareholder, Metal Tiger can partner on future projects undertaken by Eurasia in Russia.
Broken rocks picture
May 16 2016
“Platinum now becomes the next key focus of the project,” said Leon Coetzer, chief executive.

© Proactive Investors 2016

Proactive Investor UK Limited, trading as “Proactiveinvestors United Kingdom”, is Authorised and regulated by the Financial Conduct Authority.
Registered in England with Company Registration number 05639690. Group VAT registration number 872070825 FCA Registration number 559082. You can contact us here.